While NORDUnet’s November 2026 Memorandum of Understanding with South Korea’s KREONET advances East Asian research alignment around the Polar Connect trans-Arctic submarine cable, neither South Korea nor Japan has a confirmed commercial Cable Landing Party for the system yet—contrasting with rival Arctic project Far North Fiber (FNF), which has already secured Japan’s ARTERIA Networks.
Key Takeaway: Research MoUs vs. Commercial Landing Parties
Both South Korea’s KREONET (operated by KISTI) and Japan’s National Institute of Informatics (NII) are National Research and Education Networks (NRENs) rather than licensed commercial submarine cable operators. Consequently, onboarding licensed domestic telecom carriers to serve as physical Cable Landing Parties in Japan and South Korea remains a primary commercial objective of Polar Connect Step 2 (2026–2028).
1. Current Parties & Consortium Structure (Polar Connect Step 2)
The Polar Connect initiative acts as a catalyst to form a Europe-based alliance to build a resilient trans-Arctic submarine cable system and reserve 10% of the fiber capacity for European research and education. The project is currently executing Polar Connect Step 2 (24-EU-DIG-PC2), a 36-month preparatory, engineering, and commercial-structuring phase running from 2026 to 2028 and co-funded by the European Union’s Connecting Europe Facility (CEF Digital). At present, all formal beneficiaries and partners in Step 2 are European organizations:
| Organization | Role in Step 2 (2026–2028) | Core Mandate |
|---|---|---|
| Swedish Research Council (VR / Sunet) | Project Coordinator (Beneficiary) | Overall project coordination, establishing the legal ownership entity for Polar Connect, and developing the long-term operations and maintenance framework. |
| NORDUnet A/S | Beneficiary (representing Nordic NRENs: Sunet, CSC, Sikt, DeiC, RHnet) | Developing financing strategies, designing the pan-Arctic network architecture, coordinating with landing parties and backhaul partners, and leading regulatory and permitting work across route countries. |
| Swedish Polar Research Secretariat (SPRS) | Beneficiary | Providing Arctic operational expertise, conducting icebreaker-based seabed surveys, and coordinating logistical and environmental groundwork. |
| GlobalConnect AB | Beneficiary (with commercial support group including Tusass, Cinia, DSCC, and Tampnet) | Conducting market studies, drafting a provisional business plan, and delivering the formal assessment report on commercial landing parties and terrestrial backhaul connectivity. |
| CSC — IT Center for Science (Finland) | Beneficiary | Contributing high-performance computing (HPC) and international research network connectivity expertise. |
| GÉANT Association | Associated Partner | Engaging with the broader European research and education community to aggregate demand and support dedicated R&E fiber capacity. |
2. Existing Polar Connect MoUs Across Europe and East Asia
To establish a sovereign, low-latency Arctic corridor connecting Europe and East Asia while bypassing congested southern maritime chokepoints—such as the Suez Canal, Red Sea, and Strait of Malacca—NORDUnet has signed three bilateral Memoranda of Understanding with national research network operators:
Portugal’s FCT
Signed with Portugal’s Foundation for Science and Technology (FCT) to expand international research connectivity cooperation around Polar Connect, linking Southern Europe’s Atlantic gateways with the northern Arctic corridor.
Japan’s NII
Signed with Japan’s National Institute of Informatics (NII) under the title Strengthening Europe – Japan Digital Gateway with Polar Connect, committing both sides to advancing resilient, sovereign direct interconnection via the Arctic route.
South Korea’s KREONET
Signed between NORDUnet and KREONET to renew and expand their intercontinental connectivity partnership between the Nordic countries and the Republic of Korea with Polar Connect as the next step.
3. Status on Japan Landing: Polar Connect vs. Far North Fiber (FNF)
Japan is positioned as a primary East Asian anchor in Polar Connect’s architectural planning, supported by the July 2023 European Commission–Japan Memorandum of Cooperation on submarine cables for secure, resilient and sustainable global connectivity. However, the commercial landing status in Japan differs sharply between the two competing trans-Arctic cable projects:
Polar Connect: No Confirmed Japanese Landing Party Yet
- Research Alignment Only: While NORDUnet holds a bilateral MoU with Japan’s NII and the Polar Connect team has engaged Japanese telecom carriers (including ARTERIA Networks) during industry consultations, no Japanese telecom operator has formally joined the Polar Connect consortium or signed a Cable Landing Party agreement.
- 2026–2028 Commercial Window: Under Polar Connect Step 2, NORDUnet and GlobalConnect are still structuring the project’s legal entity and negotiating binding landing-party and terrestrial backhaul agreements.
Far North Fiber (FNF): Confirmed Japanese Landing Party
- Confirmed Consortium Partner: The competing Far North Fiber (FNF) project—a ~14,000–15,000 km submarine cable traversing the Arctic’s Northwest Passage from Japan via Alaska and Canada to Ireland and Scandinavia—already has a confirmed Japanese commercial co-founder and landing party in ARTERIA Networks Corporation.
- Joint Venture & Supplier Structure: Established in 2022 by Finland’s Cinia Oy, Alaska’s Far North Digital, LLC, and Japan’s ARTERIA Networks, with Alcatel Submarine Networks (ASN) contracted as principal system supplier.
- Cross-Project Overlaps: Within FNF, ARTERIA serves as the Japanese terminal landing and backhaul partner. Notably, NORDUnet signed a Letter of Intent in December 2022 for one fiber pair on FNF, while Cinia participates in both FNF and GlobalConnect’s commercial support group for Polar Connect.
4. Engagements with South Korean Landing Parties
Just as NII cannot act as a commercial Cable Landing Party in Japan, KREONET is South Korea’s government-funded National Research and Education Network (operated by KISTI) and does not hold a facilities-based international submarine cable landing license.
- Division of Roles: KREONET acts as an anchor R&E demand aggregator and bilateral policy coordinator—mirroring NORDUnet and GÉANT on the European side—while NORDUnet and GlobalConnect lead commercial landing-party negotiations during Step 2.
- Outreach to Licensed Korean Carriers: Landing Polar Connect in South Korea requires onboarding a licensed facilities-based Korean international carrier. The Polar Connect team has already initiated direct commercial discussions with South Korea’s primary international subsea operators, including Korea Telecom (KT) and SK Broadband, alongside bilateral policy consultations between European and South Korean science and telecom stakeholders.
5. Technical & Commercial Linking Options for South Korea
As NORDUnet and GlobalConnect finalize Polar Connect’s legal ownership entity and commercial consortium structure during the 2026–2028 Step 2 window, South Korea’s physical interconnection will likely take one of two architectures:
A licensed South Korean facilities-based carrier (such as KT or SK Broadband) joins Polar Connect’s commercial consortium as the official Korean Cable Landing Party. South Korea connects directly to the trans-Arctic system via a subsea branching unit, with KREONET utilizing dedicated R&E fiber capacity or spectrum.
Leveraging NORDUnet’s February 2026 MoU with Japan’s NII and ongoing commercial outreach in Japan, Polar Connect lands its primary East Asian terminal in Japan and extends capacity onward to South Korea via existing or newly built Korea–Japan submarine cables operated by regional carriers.