1. Evolution of the VTS Project: From 2024 Initiation to 2030 Target

Originally conceived as a direct bilateral trunk connecting Vietnam and Singapore, the Vietnam–Thailand–Singapore Submarine Cable (VTS) has undergone significant structural delays and scope expansion over the past two and a half years.

Vietnam-Thailand-Singapore Cable System (VTS, missing Thailand branch), Image Courtesy: Viettel

 

Milestone Key Participants Project Development & Schedule Impact
April 2024
Project Initiation
Viettel & Singtel Signed an MoU to co-develop VTS as an 8-fiber-pair (8FP) DWDM trunk linking Vietnam (managed by Viettel) and Singapore (managed by Singtel), with an initial completion target of Q2 2027.
September 2026
Consortium Restructuring
Gulf Development (GULF), Singtel, & AIS Formalized investment to add a dedicated Thailand branch and landing station operated by AIS, transforming VTS into a Vietnam–Thailand–Singapore network and pushing the expected RFS date back by three years to 2030.
November 12, 2026
Vietnamese Co-Investment
FPT Telecom Board resolution authorized joint investment in VTS, though specific financial terms, wet-plant supplier awards, and construction start dates remain undisclosed.

Why VTS Has Been Delayed

Despite strong political backing under Vietnam’s digital infrastructure strategy, VTS stalled between 2024 and mid-2026—not due to South China Sea permitting, as the route is deliberately designed to avoid the Nine-Dash Line, but because of prolonged consortium structuring, delays in securing a binding commitment for the Singapore landing despite Singtel’s role as an initial partner, and commercial feasibility hurdles. To strengthen the project's business case and broaden anchor demand, the partners expanded the scope to incorporate Thailand’s Eastern Seaboard (bringing in Gulf Development and AIS) and onboarded FPT Telecom, pushing the targeted Ready-for-Service date from 2027 back to 2030. Consequently, what began as a fast-track bilateral project targeting 2027 has evolved into a multi-party regional build that is still awaiting confirmed wet-plant supplier contracts and financial close ahead of its 2030 target.

2. Subsea Cable Portfolios: Viettel vs. FPT Telecom

FPT Telecom’s entry into VTS highlights the contrasting infrastructure strategies of Vietnam’s major telecom operators. While state-owned military giant Viettel controls roughly 65% of Vietnam’s international bandwidth capacity and operates multiple legacy and next-generation systems, FPT Telecom has only recently pivoted from leasing third-party bandwidth to becoming a direct consortium co-investor and Cable Landing Station (CLS) operator:

Dimension Viettel Group FPT Telecom
In-Service Subsea Cables
  • AAG (Asia-America Gateway)
  • APG (Asia-Pacific Gateway)
  • TGN-IA (Tata TGN-Intra Asia)
  • AAE-1 (Asia-Africa-Europe 1; ~$50M investment)
  • ADC (Asia Direct Cable; entered service late 2024)

No proprietary in-service consortium cables. Historically relied on capacity leases and IRUs across existing international systems (such as AAG, APG, and AAE-1) operated by domestic and foreign carriers.

Undergoing & Pipeline Cables
  • ALC (Asia Link Cable): Co-investor alongside regional carriers.
  • VTS: Co-founder and Vietnamese landing party (target 2030).
  • National 2030 Mandate: Tasked with deploying five new international subsea cables between 2025 and 2030.
  • ALC (Asia Link Cable): Co-investor and landing party (nearing completion).
  • VTS: Joint investor approved via November 2026 board resolution (target 2030).
Vietnamese Cable Landing Stations (CLS) Operates major landing hubs at Vung Tau CLS (landing TGN-IA, AAE-1, and planned VTS) and Quy Nhon CLS (landing ADC). Operates the new Da Nang CLS for the Asia Link Cable (ALC)—FPT Telecom’s first proprietary international submarine landing station.
Strategic Focus Wholesale capacity dominance, sovereign backbone security, and multi-landing route redundancy across northern, central, and southern Vietnam. Securing dedicated, low-latency international bandwidth to support FPT’s hyperscale data centers, cloud services, and AI infrastructure in Ho Chi Minh City and Hanoi.

 

3. Structural Challenges Facing Vietnam–Singapore Subsea Initiatives (VTS, MViSTA & Parallel Routes)

Under Vietnam’s national telecommunications strategy, the country aims to expand from five legacy operational subsea systems to at least 15 submarine cable systems delivering over 334 Tbps of capacity by 2030. However, dedicated Vietnam–Singapore projects—including both VTS and the competing private-led MViSTA (Malaysia–Vietnam–Thailand–Singapore) system—face four major structural hurdles:

1. Singapore Landing Bottlenecks & Commercial Feasibility

Unlike systems traversing disputed deep-water corridors, VTS avoids South China Sea permitting friction by routing clear of the Nine-Dash Line. Instead, its primary hurdles have been securing a binding commitment and regulatory clearance for the Singapore landing—even with Singtel as an initial partner—and proving standalone commercial feasibility, which ultimately required adding a Thailand branch (via Gulf Development and AIS) to anchor regional capacity demand. By comparison, the rival $300M+ MViSTA project (targeting 2028–2029 RFS) routes further west via the Gulf of Thailand and Malay Peninsula to diversify landing options into Johor and Tuas.

2. Multi-Party Consortium Alignment & Scope Creep

As demonstrated by VTS’s slip from Q2 2027 to 2030, balancing bilateral Vietnamese–Singaporean priorities with multi-country branching demands (such as integrating Thailand’s AIS into VTS, or aligning four jurisdictions across Vung Tau, Rayong, Songkhla, Pengerang/Johor, and Tuas in MViSTA) slows down Final Investment Decisions (FID), vendor selection, and financial close.

3. Global Wet-Plant Bottlenecks & Overlapping Supply

Global shortages of specialized cable-laying vessels, marine survey ships, and optical repeaters have driven up capital costs and extended delivery lead times across Southeast Asia. At the same time, new Vietnam–Singapore cables must compete for anchor tenants against newly activated high-capacity systems (ADC and SJC2), upcoming ALC capacity and other new subsea cables running inside the 9-dash line, and VNPT’s VSTN terrestrial cross-border fiber route to Singapore via Laos, Thailand, and Malaysia.

4. Domestic Landing & Backhaul Concentration

Vietnam’s submarine cables have historically clustered around Vung Tau and Quy Nhon, creating single-point vulnerability to vessel anchor drags and severe weather. Ensuring that VTS and MViSTA deliver genuine network resilience requires pairing new subsea landings with geographically diverse Cable Landing Stations (such as FPT’s Da Nang facility) and hardened domestic terrestrial backhaul.