Keppel Ltd. (Keppel) announced today that the Bifrost Cable System (Bifrost) has been granted a submarine cable landing license by the United States Federal Communications Commission (the US FCC). The Bifrost cable system is expected to be ready for commercial service in 2H 2025.

According to the US FCC public notice, the cable landing license for the Bifrost cable system was granted on January 17, 2025, to the applicants comprising Edge Cable Holdings USA, LLC (Edge USA, a direct, wholly owned subsidiary of Meta Platforms, Inc), AMCS LLC (AMCS,  an indirect, wholly owned subsidiary of Amazon.com, Inc.), Keppel Midgard USA (a wholly owned subsidiary of Keppel Midgard Holdings Pte Ltd), and PT Telekomunikasi Indonesia International (Telin).

Spanning over 20,000km, Bifrost is the world’s first subsea cable system that directly connects Singapore to the west coast of North America via Indonesia through the Java Sea and Celebes Sea. A subsea cable landing license must be obtained prior to landing a submarine cable to connect continental United States with any foreign country. The achievement of the US FCC cable landing license marks the final approval in an extensive transnational regulatory approval process, paving the way for Bifrost’s successful deployment.

Keppel released that Bifrost had commenced system commissioning and acceptance testing on 21 January 2025, and is expected to be ready for commercial service in 2H 2025.

Keppel said the Bifrost cable system is first subsea cable system linking Southeast Asia to the United States to be approved in the past eight years. In 2015, the USFCC granted submarine cable landing license for the SEA-US cable system connecting Indonesia, the Philippines, Guam, Hawaii and Los Angeles.

Bifrost’s cable landing station in Singapore will be sited at Keppel DC REIT’s SGP 5 data centre in Jurong.

Bifrost is part of Keppel's end-to-end connectivity ecosystem, spanning power, off-grid solutions, green energy, cooling, subsea cable connectivity and data centre solutions. Critical digital infrastructure such as Bifrost will not only boost the performance and reliability of Keppel's data centre offerings but also position the Company at the forefront of the digital economy.

Keppel released that it was assigned five out of a total of 12 fibre pairs with its share of cost being US$350 million. The five fibre pairs are jointly owned by Keppel and its private fund co-investors through a 40-60 joint venture. Of these, two fibre pairs have since been committed to customers through Indefeasible Rights of Use (IRU) for 25 years, while IRUs for the remaining three fibre pairs are currently being negotiated with potential customers. Keppel said the expected Internal Rate of Return for their investment in the Bifrost cable system has risen to over 30% p.a.

According to the US FCC public notice, Keppel entities own 5.518 fiber pairs on the Bifrost main trunk connecting Singapore, Guam and Grover Beach in California, while Meta and Telin each owns 6.1289 fiber pairs and 0.3553 fiber pairs. Keppel entities owns all of the six fiber pairs on the Bifrost Oregon Branch, landing at the Winema cable landing station owned by Wave Business Solutions, LLC (d/b/a Astound Business Solutions) (Astound) and controlled by Amazon.

In addition, when Bifrost is completed in 2H 2025, Keppel will continue to operate and maintain its five fibre pairs over a period of 25 years, for which the Company stands to derive a stream of long-term recurring income.

Beyond Bifrost, Keppel, together with its private funds including Keppel Asia Infrastructure Fund II, are exploring opportunities to develop more cable systems connecting various geographies. These initiatives are part of Keppel's broader strategy to enhance global connectivity and provide digital infrastructure solutions, leveraging its integrated ecosystem to meet the evolving needs of countries, businesses and consumers, and deliver the best risk-adjusted returns to investors.