Greenland Connect is a 4,600 km submarine cable system linking Greenland to Iceland and Canada.
Greenland Connect lands at:
In Iceland, the Greenland Connect cable system terminates in Verne Global's data center. Verne Global was acquired by British investment firm Digital 9 Infrastructure plc (D9) for a valuation of approximately £231 million in cash in September 2021. Ardian, a France-based, independent private equity investment company, completed the acquisition of 100% of shares of Verne Global for $575 million in March 2024.
The Greenland Connect cable system is owned and operated by Tusass A/S (formerly known as TELE Greenland A/S or TELE-POST), the sole telecom operator in Greenland.
TELE Greenland A/S was created in 1997 through the merging of TELE Greenland and Kalaallit Allakkeriviat (Greenland Postal Service). After the merger, Kalaallit Allakkeriviat became a business unit and was renamed as POST Greenland. The common designation "TELE-POST" for both business came into being. TELE-POST was rebranded as Tusass A/S in 2021. Tusass is Greenlandic slang for "talk to you later".
In 2007, TELE Greeland selected Alcatel-Lucent Submarine Networks (ASN) to deploy the Greenland Connect project, at a cost of Euro 90 million for a turnkey contract.
The Greenland Connect cable system consists of two trunk segments:
Each segment of the Greenland Connect consists of 2 fiber pairs, initially designed with 96 x 10 Gbps DWDM technology, for a system capacity of 1.92 Tbps.
The Greenland Connect cable system was ready for service on March 23, 2009.
In April 2016, TELE-POST selected Alcatel-Lucent Submarine Networks (ASN) to build the Greenland Connect North (GCN), a 680 km of domestic extension of the Greenland Connect,
The Greenland Connect North cable lands at:
The Greenland Connect North cable system consists of two fiber pairs as well, initially designed with 96 x 10 Gbps DWDM technology, for a system capacity of 1.92 Tbps.
The Greenland Connect North cable reached Aasiaat on 8 October 2017. Services using the Greenland Connect North cable launched on 11 December 2017.
In late 2016, Tele Greenland selected Huawei Marine to upgrade the Greenland Connect and the Greenland Connect North cable systems with 100Gbps DWDM technology. Huawei Marine supplied and installed Submarine Line Terminal Equipment (SLTE) for the existing Greenland Connect system and the new Greenland Connect North cable system.
In October 2017, Tele Greenland completed the upgrade of the Greenland Connect and the Greenland Connect North cable systems with Hauwei Marine's 100Gbps DWDM technology.
The system capacity of the Greenland Connect cable system was upgraded 1.92 Tbps to 12.8 Tbps between Greenland, Iceland and Canada.
The system capacity of the Greenland Connect North cable system was upgraded to 4.8 Tbps.