According to The Business Standard, a leading daily newspaper and digital news platform based in Dhaka, Bangladesh, the first privately funded submarine cable project in Bangladesh — the $150 million Bangladesh Private Cable System (BPCS) designed to break the state monopoly on international data gateways — has been reduced to an expensive standstill by overlapping ministerial protocols, security clearances, and an unforgiving Bay of Bengal weather window.

This analysis traces the project’s origins, its innovative hybrid architecture, the inter‑ministerial paralysis that now threatens its viability, and the strategic interplay between the BPCS and the Bagha‑1 cable system, Bangladesh's another private subsea cable initiative backed by US fund.

1. Origins: Breaking the Monopoly

1.1 The State‑Owned Bottleneck

For years, Bangladesh’s international connectivity has been a textbook case of state monopoly. The Bangladesh Submarine Cable Company Ltd (BSCCL) owns and operates the country’s only international subsea connections — the SEA‑ME‑WE 4 and SEA‑ME‑WE 5 cables — and holds a stake in the future SEA‑ME‑WE 6. The BSCCL has been re-branded as Bangladesh Submarine Cables PLC (BSCPLC). Critics have long accused BSCCL of maintaining a single‑point dependency that keeps wholesale internet transit costs artificially inflated and leaves the country vulnerable to routine cable breaks. A single fault on SEA‑ME‑WE 5 in early 2024 knocked out two‑thirds of Bangladesh’s international subsea capacity and disrupted services nationwide.

Bangladesh Submarine Cable has expressed concerns that private entry will create "extreme instability" and reduce the revenue of the state-owned listed company. In a recent internal report, the company suggested that the government should set a minimum threshold to ensure state-owned cable usage does not fall below 50%.

Bangladesh Submarine Cable used to participate in consortium subsea cables, such as SWM4, SMW5 and SMW6, responsible for the heavy and whole cost long branches connecting Bangladesh with trunks of the systems. So, Bangladesh Submarine Cable's investment and cost in a subsea cable has been usually much higher than other members of the same consortium. For example, the company's total cost for the SEA-ME-WE 6 is about Tk 8.70 billion (equivalently US$100 million).

1.2 The BTRC’s 2022 Reform: Three Licences, One Goal

In a landmark liberalisation move, the Bangladesh Telecommunication Regulatory Commission (BTRC) issued three licences in September 2022 to establish, maintain and operate private submarine cables. The recipients were Summit Communications Ltd (the country’s largest fibre‑optic network infrastructure provider), CdNet Communications Ltd (an International Terrestrial Cable operator), and Metacore Subcom Ltd (a specialist domestic telecom licensee).

The three companies subsequently formed the Bangladesh Private Cable System (BPCS) consortium, pooling their capital and commercial momentum to build the nation’s first privately owned international subsea route. The BTRC imposed a firm “roll‑out obligation” deadline of 31 August 2026, requiring the private cable to be commercially active by that date — a deadline that now hangs by a thread.

2. Project Architecture: A Shortcut to Singapore

Rather than financing a full‑length transpacific cable, BPCS engineered a hybrid “shortcut” architecture that dramatically reduced both cost and construction time.

2.1 The UMO Trunk and the Cox’s Bazar Branch

The consortium formed a partnership with Singapore’s Campana Group to piggyback on Campana’s existing UMO cable system. UMO is a 2,227‑km submarine trunk running from Tuas, Singapore, to Thanlyin, Myanmar, supplied and deployed by HMN Tech (formerly Huawei Marine Networks). BPCS is laying a 1,300‑km branch cable from a branching unit on the UMO trunk northwards through Myanmar’s Exclusive Economic Zone to a newly built landing station in Cox’s Bazar, Bangladesh. Once the branch is connected, Bangladesh gains direct, low‑latency access to Singapore’s dense telecom ecosystem without having to build an entirely new transoceanic line.

2.2 Dual‑Supplier Strategy: HMN Tech + Nokia

The system relies on a split‑vendor design that separates the physical wet plant from the electronic dry plant — a strategic choice that balances cost efficiency with international security requirements.

  • Wet Plant (HMN Tech): The physical subsea cable, deep‑water armouring and underwater repeaters were manufactured and deployed by China’s HMN Tech. This approach drastically lowered baseline CAPEX.
  • Dry Plant (Nokia): The BPCS consortium contracted Nokia to supply the Submarine Line Terminal Equipment (SLTE) installed inside both the Cox’s Bazar Cable Landing Station and the Tuas Cable Landing Station in Singapore. Nokia’s Western‑approved platform “lights up” the three fibre pairs — each delivering at least 15 Tbps of capacity, for a total of 45 Tbps — while providing a secure cyber perimeter that satisfies the strict security vetting requirements of Western hyperscalers such as Meta, Google and Amazon.

By swapping out Chinese terminal electronics for a Western SLTE, the consortium insulated the logical data layer from the geopolitical objections that otherwise prevent HMN‑Tech‑built cables from carrying traffic for US‑based cloud giants.

3. Financial Commitments

The projected total cost to launch and integrate the BPCS system sits between $150 million and $160 million. According to The Business Standard,  as of late 2025, the consortium had already invested $53 million (approximately Tk650 crore), including:

  • $43.76 million paid to the trunk owner Campana, comprising $36 million in IRU fees for a 25‑year lease of the UMO trunk capacity and $7.96 million in long‑term advance operational maintenance charges.
  • Additional capital spent on licensing, VAT, feasibility studies, route surveys, and construction of the Cox’s Bazar landing station and beach manhole.

4. The Regulatory Impasse: Inter‑Ministerial Gridlock

4.1 The Bottleneck: Vessel Clearances

The BPCS consortium has reached all critical technical milestones. These include a comprehensive feasibility study, a detailed subsea route survey completed in April 2025, the demarcation of the route from Myanmar‘s Exclusive Economic Zone to Cox’s Bazar, and the activation of the Singapore‑Myanmar segment. The project is in a “shovel‑ready” phase, with the landing station and beach manhole under construction. Specialised cable‑laying vessels and a team of international experts have been contracted and are awaiting final approval.

The main obstacle is not technical but bureaucratic. According to The Business Standard, on 31 March 2026, the consortium formally sought no‑objection clearance (NOC) for Panama‑ and Indonesia‑flagged vessels to enter Bangladeshi territorial waters. However, the consortium had approached the government as early as December 2024, when a request for five Chinese ships was filed, according to TIMES of Bangladesh. Ten months of repeated follow‑ups have failed to secure a decision, pushing the project into what one consortium member describes as “a procedural loop”.

The NOC requires a comprehensive sweep by multiple agencies. The Ministry of Power and Energy, Ministry of Shipping, Ministry of Fisheries and Livestock, Ministry of Defence and the Armed Forces Division have already permitted the request. However, the clearance has been stuck at the Ministry of Home Affairs and the Ministry of Environment.

4.2 The Protocol Gap and Ministry Interface Issue

The paralysis stems from a lack of formal inter‑ministerial referral. A foreign ministry official explained that, under standard protocol, one ministry cannot act on a letter issued by an agency under another ministry. The consortium had been asked to obtain authorisation from the Posts, Telecommunications and Information Technology Ministry, but no such communication had been received as of late April 2026.

Telecom Secretary Bilquis Jahan Rimi confirmed that the ministry had not received any letter on the matter and that a decision would be made once it did. However, official documents show that the consortium had already written to that ministry in September 2025 seeking inter‑ministerial support, well before the March 2026 NOC application. The Bangladesh Telecommunication Regulatory Commission (BTRC) also wrote to relevant government offices in December 2024 and copied the Posts and Telecommunications Division on the correspondence. A BTRC commissioner has since denied any lack of cooperation, pointing to the commission’s support in land coordination for the landing station.

The Ministry of Foreign Affairs has stated that it cannot process the request without a recommendation from the sponsoring ministry. The head of the Foreign Ministry‘s Maritime Affairs Unit noted that if the Posts and Telecommunications Division had issued a recommendation, there would be no reason for delay, adding that the Ministry had already cleared two similar NOC requests. A special assistant to the Chief Adviser for the telecom ministry has also publicly stated that no official file has reached his office. As a result, the application remains stalled with no single ministry taking ownership of the clearance process.

5. The Weather Window: Why the Bay of Bengal Turns a Delay into a Disaster

What elevates this administrative delay from a routine regulatory hurdle to an existential threat for the $53 million investment is the rigid, unforgiving climate cycle of the Bay of Bengal.

Subsea cable installation and seabed trenching require highly stable maritime conditions. In the Bay of Bengal, marine construction is technically feasible only between November and mid‑May, when ocean swells are calm. From June through October, the region enters the intense monsoon season, characterised by severe cyclonic risks, rough seas and heavy river siltation that makes precision subsea cable burial impossible.

Because the inter‑ministerial gridlock dragged past the critical April/May pre‑monsoon weather window, the contracted specialised vessels missed their deployment slots. The consequences are severe:

  • A one‑year roll‑forward: The project is effectively pushed back to the next calm weather window opening in late 2026, which will almost certainly breach the government’s 31 August 2026 roll‑out deadline.
  • Demurrage penalties: The consortium must absorb compounding maritime demurrage fees to keep specialised international cable ships and engineering crews on idle retainers.
  • Prolonged monopoly: The delay leaves Bangladesh entirely dependent on BSCCL’s pipelines (SEA‑ME‑WE 4 and 5), extending the country’s vulnerability to abrupt outages and keeping wholesale internet transit costs artificially inflated.

“We have already invested nearly 50% of the total project cost. We are stuck in a complex situation. If the government did not want private submarine cables, why were we encouraged to spend millions on infrastructure and licences?” — Md Arif Al Islam, Managing Director of Summit Communications.

6. BPCS and Bagha‑1

6.1 What the US Actually Funded: Bagha‑1

In May 2024, prior to the launch of the BPCS project, the U.S. Trade and Development Agency (USTDA) awarded a feasibility study grant to CdNet Communications to explore the Bangladesh International Submarine Cable, named Bagha‑1. Under the grant rules, CdNet was required to select an American company to conduct the strategic engineering, and chose Florida‑based APTelecom LLC.

The USTDA grant was explicitly pushed out under major White House and State Department geopolitical initiatives, including the Digital Connectivity and Cybersecurity Partnership (DCCP) and the Partnership for Global Infrastructure and Investment (PGII). The explicit goal was to help Bangladesh integrate “trusted”, Western‑aligned subsea infrastructure.

6.2 Why Bagha‑1 Has Stalled

The Bagha‑1 feasibility study was a “greenfield” exploration of an entirely new cable crossing thousands of kilometres of ocean floor. Building such a cable from scratch would take 3–5 years — a timeline that would cause the operators to miss the BTRC’s 2026 roll‑out deadline and face severe penalties.

Rather than competing against Summit and Metacore while waiting for the slow Bagha‑1 study to yield results, CdNet effectively merged its business intent into the BPCS consortium. By pooling resources, CdNet achieved everything it wanted from Bagha‑1 at a fraction of the time and cost:

  • The 1,300‑km branch piggybacking off Campana’s existing UMO trunk is far faster and cheaper than a greenfield cable.
  • The $150 million total cost is split three ways, giving CdNet a dedicated fibre pair delivering 15+ Tbps of private capacity for its own commercial use.
  • The environmental, desktop and bathymetric data collected for the Bagha‑1 study (including the Cox’s Bazar landing zone and the silt‑heavy waters of the Bay of Bengal) was utilised to de‑risk the engineering phase for the BPCS branch.

CdNet has not officially announced that Bagha‑1 is dead. But the market reality is that Bagha‑1 as a standalone cable project has effectively been absorbed into the BPCS consortium. Rather than holding a 100% stake in a delayed, unbuilt project, CdNet chose to hold a 33.3% stake in a joint vehicle that already has its HMN Tech wet plant purchased, its Nokia security electronics integrated, and its landing station advanced.

7. The Nokia Factor: A Geopolitical “Security Shield”

The consortium’s decision to contract Nokia for the dry plant equipment, even while the wet plant is supplied by China’s HMN Tech, is a deliberate and sophisticated geopolitical hedge. The Nokia SLTE performs two critical functions:

  1. Operational: It “lights up” the three fibre pairs, enabling the 45 Tbps capacity.
  2. Compliance: By using Western‑approved terminal electronics, the consortium establishes a secure cyber perimeter that makes the cable acceptable to U.S. and allied hyperscalers. Any cable that relies exclusively on Chinese electronics — no matter how well‑built — would be barred from carrying sensitive data for Meta, Google or Amazon. The hybrid architecture insulates the logical data layer from the geopolitical objections that otherwise plague HMN‑Tech‑built cables.

In short, Nokia’s SLTE is the security passport that allows a Chinese‑supplied cable to carry Western traffic. Without it, the entire BPCS project would be commercially dead on arrival, regardless of whether the vessels ever get permission to sail.

8. Analyst Assessment

8.1 A Credible De‑risking Strategy, Undermined by Bureaucracy

From a technical and commercial standpoint, BPCS was impeccably structured. The hybrid wet‑plant/dry‑plant split reduced costs while preserving access to Western cloud markets. The Campana “piggyback” shortcut accelerated the timeline. The Nokia contract provided a security shield.

All of that engineering sophistication, however, is useless if specialised vessels cannot enter Bangladeshi waters. The inter‑ministerial protocol gap is not a technical problem; it is a governance failure for which the consortium bears no responsibility.

8.2 The Weather Window as a Force Majeure Risk

The Bay of Bengal’s narrow November‑to‑mid‑May installation window is a known environmental constraint. Missing the 2026 pre‑monsoon window pushes commercial service to 2027, triggering a BTRC roll‑out breach and potentially exposing the consortium to financial penalties. The project is now in a race against the weather — and the bureaucratic clock is not on its side.

8.3 Bagha‑1: Absorbed, Not Abandoned

Bagha‑1 is not so much dead as repurposed. The USTDA study data has been fully integrated into the BPCS engineering process. The US goal of introducing “trusted” subsea infrastructure into Bangladesh is still being served — just through a different corporate vehicle. For Washington, BPCS is an imperfect but still acceptable vehicle for injecting Western‑aligned connectivity into the country, provided the Nokia SLTE remains the controlling logical layer.

8.4 The Unanswered Question

The most troubling question for the BPCS consortium, and for Bangladesh’s broader digital future, is this: If the government could not process a routine vessel NOC within nine months, what confidence does it offer for the next 25 years of private subsea infrastructure investment?

Without a reliable, predictable permitting process, no amount of private capital will be willing to bet on Bangladesh’s digital transformation.

9. Conclusion

The Bangladesh Private Cable System was designed as a model of efficient, private‑sector subsea infrastructure: a low‑cost, high‑capacity “shortcut” intended to introduce competition into the international gateway market and potentially reduce internet costs for consumers. However, the project has encountered significant delays due to a combination of inter‑ministerial coordination requirements and the narrow seasonal weather window for cable installation in the Bay of Bengal.

The consortium has fulfilled its technical and financial obligations — securing licences, raising capital, completing a hybrid wet‑plant/dry‑plant architecture with HMN Tech and Nokia, and constructing a landing station in Cox’s Bazar. Nevertheless, the vessels required for cable laying have not yet received the necessary clearances, causing the project to miss the pre‑monsoon deployment period. This postponement now makes it unlikely to meet the BTRC’s August 2026 roll‑out deadline, and the consortium faces additional demurrage costs.

The Bagha‑1 feasibility study, funded by the USTDA, has been effectively absorbed into the BPCS project, with its environmental and route data utilised to de‑risk the engineering phase. Bagha‑1 as a standalone cable has not progressed, but its underlying objective of introducing Western‑aligned connectivity into Bangladesh continues to be served through the BPCS consortium, particularly via the Nokia SLTE security framework.

Whether the required clearances will be issued before the next weather window remains to be seen. The coming months will determine if Bangladesh’s first private international subsea cable can move forward and offer an alternative to the state‑owned infrastructure.