Nexans has been tasked to carry out repair of the EstLink 2 electricity subsea cable between Finland and Estonia. The repair may cost €50 million to €60 million and the EstLink 2 is expected to start operating again in July.
Estlink 2 is the second high-voltage direct current (HVDC) interconnection between Finland and Estonia, in addition to the first one Estlink 1 completed in 2006. With an investment of approximately €320 million for an electricity transmission capacity of 650 MW, Estlink 2 was officially launched for commercial operations in February 2014. The total cable length is 170 kilometers long, of which 145 kilometers is submarine cable, 14 kilometers overhead on the Finnish side and 12 kilometers underground in Estonia. The electricity subsea cable weighs approximately 80 kg per metre.
This Estlink 2 was damaged on 25 December 2024. The the Cook Islands-flagged tanker Eagle S was suspected to be responsible for the damage, which dragged its anchor over the seabed.
The Eagle S has been linked to the so-called “shadow fleet” used by Russia to bypass EU sanctions. The Eagle S tanker was seized during the investigation but left Finnish waters in March. The reason for abandoning the seizure claim was the associated unreasonably high costs. The cost of keeping the ship under arrest is hundreds of thousands of euros per month, plus the arrest guarantee of one million euros and several other additional costs, as a result of which the costs arising from the arrest may ultimately be greater than the value of the ship. In addition, it is extremely difficult to sell the ship during the litigation.
There was another damage of the Estlink 2 on January 26, 2024, repaired until August 31.
Cable manufacturer Nexans began the EstLink 2 repair work on May 18. Over the weekend, insulation measurements were carried out on segments of the EstLink 2 cable on both the Estonian and Finnish sides. And then Nexans began physical work in the Gulf of Finland from the vessel Deep Cygnus.
The preparatory work to repair the damaged section of the subsea cable had taken place from February to April. During these preparations, the damaged portion of the cable was lifted from the sea and cut out. The remaining cable was tested to ensure it was in working condition. The goal of the preparatory phase was to minimize risks associated with the repair work starting in May and to fine-tune the technical details.
The repair will involve replacing the damaged section with a new subsea cable to be installed along approximately one kilometer of the seabed. The repairs will utilize previously manufactured and delivered spare cable and repair joints.
The estimated cost of the EstLink 2 repair is €50-60 million, to be split equally between Estonia's system operator Elering and Finland's system operator Fingrid. It was reported that the cost of the repair of its damage in last January totaled over €30 million.
The increased cost this time is due to the decision to use a general-purpose construction vessel owned by a third party — rather than a specialized cable-laying ship — in order to speed up the process. The vessel had to be specially adapted for the specific requirements of the EstLink 2 cable. Using the typical repair vessel would have pushed the work back to the end of the year.
Elering and Fingrid have planned to sue the shipowner for compensation for repair costs. But the trial could last up to five or six years, so system operators will initially have to cover the repair costs themselves in order to quickly restore the connection.
The Estlink 2 electricity link is expected to return to commercial use in July upon completion of the repair and the tests ensuring the functionality of the cable connection is achieved.
Update:
On August 6, 2025, Nexan announced the completion of the repair of the Estlink 2 interconnector under contract for Fingrid, Finland’s transmission system operator. The offshore repair, involved replacing a one-kilometer section of subsea cable, was completed safely and on schedule—with full alignment between Nexans’ technical execution and Fingrid’s operational requirements.