On April 9, 2026, the U.S. Federal Communications Commission (FCC) issued a draft Notice of Proposed Rulemaking (NPRM) (tentatively titled Protecting Against National Security Threats in Domestic Telecommunications Service) for a vote scheduled on April 30, 2026. The FCC NPRM seeks to bar China Mobile, China Telecom and China Unicom from operating data centers and Points of Presence (PoPs) in the U.S., prohibit interconnection with Chinese carriers, and extend restrictions to any carrier using Huawei/ZTE equipment. This is the most significant expansion of the "Covered List" regime since 2019 — transforming voluntary guidelines under "Clean Network" policy into mandatory legal exclusion.

1. The April 2026 NPRM: "Logical and Physical Isolation"

Data Center & PoP Operations Ban

Prohibits entities that are identified on the
“Covered List” (including China Mobile, China Telecom, China Unicom, etc) from operating data centers and Points of Presence (PoPs) within the U.S., directly targeting their remaining physical infrastructure including cloud nodes and PoP facilities.

Interconnection Prohibition

Bars U.S. carriers (and any carrier operating in the U.S.) from interconnecting with "Covered List" entities, effectively isolating Chinese carriers from the U.S. telecom ecosystem.

Affiliate Expansion

Extends existing service bans to certain affiliates of companies on the national security list, preventing rebranding or subsidiary circumvention.

Vendor-Based Exclusion

Would bar carriers from interconnecting with any company using equipment from Huawei, ZTE or other "Covered List" vendors — creating a cascading exclusion effect.

The FCC plans to hold an initial vote on the proposal at its April 30, 2026 meeting. A companion proposal scheduled for the same day would ban all Chinese laboratories from testing electronic devices for use in the U.S., including smartphones, cameras and computers.

2. Historical Context: Evolution of FCC Restrictions

The April 2026 NPRM represents the fourth major phase of FCC action against Chinese telecommunications operators since 2019.

Date Action Regulatory Consequence
2019 The FCC rejected China Mobile's application for domestic and international section 214 authorizations to provide U.S. telecommunications services Denied market entry on national security grounds
2021 The FCC revoked domestic and international section 214 authorizations for China Unicom, Pacific Networks and ComNet Existing operations terminated
2022 The FCC revoked China Telecom Americas' operating 214 authorization Last major carrier operating license revoked
April 2024 The FCC restored net neutrality rules to regulate Internet service providers (ISP) Bans Chinese carriers from provision of broadband internet access service (BIAS) in the US
August 2025 The FCC voted and adopted the Report and Order and Further Notice of Proposed Rulemaking (FNPRM) on submarine cable landing license rules, including a presumption disqualifying condition that a foreign adversary applicant is not qualified to hold a cable landing license Presumptively precludes the grant of a submarine cable application filed any Chinese applicant
October 2025 The FCC issued an Order to Show Cause against HKT/PCCW Global, a Hong Kong-based carrier. This signaled that the FCC now views Hong Kong carriers with the same suspicion as mainland entities. Extended restrictions to Hong Kong-based entities
December 2025 FCC issued orders on robocall database certifications, threatening network ban Regulatory pretext for potential removal from Robocall Mitigation Database (RMD)
April 2026 NPRM targeting data centers and PoP interconnections Expands restrictions to digital infrastructure and interconnection rights

The revoke / rejection of 214 authorizations and the restoration of net neutrality prevented the Chinese carriers from providing public telecom services but allowed them to continue "private" wholesale transit/peering, Point of Presence (PoP) and data center operations.

The April 2026 NPRM is the direct response to the "persistence" of these Chinese carriers in U.S. data centers and Points of Presence (PoPs) even after their retail licenses were revoked

 

3. The "Covered List" Framework

The April 2026 NPRM operates within the FCC's existing "Covered List" framework, established under the Secure and Trusted Communications Networks Act of 2019 and subsequent FCC proceedings (WC Docket No. 18-89).

Entity Type Included Entities Regulatory Effect
Equipment Providers Huawei, ZTE, Hytera, Hikvision, Dahua, etc Universal Service Fund (USF) purchase prohibition; equipment removal mandates
Telecom Carriers China Mobile, China Telecom, China Unicom Operating authorizations revoked; now subject to data center/PoP restrictions
Affiliates Pacific Networks, ComNet, HKT (proposed) Service bans extended to subsidiary entities

The Covered List mechanism originally prohibited use of USF funds to purchase equipment from designated Chinese vendors. The 2026 NPRM extends this logic from procurement restrictions to operational prohibitions — moving from "what carriers can buy" to "where carriers can locate infrastructure and who they can connect with."

 

4. 2026 NPRM vs. Clean Network Program (2020)

The 2026 NPRM is essentially the codification and enforcement of the original (and largely aspirational) "Clean Network" policy introduced by the State Department in 2020.

Dimension Clean Network Program (2020) 2026 NPRM
Announcement August 2020, under Trump‘s first administration April 2026, under current administration
Legal Basis Executive branch policy guidance; voluntary "trusted" lists, non-binding guidelines FCC formal rulemaking (NPRM); legally binding and enforceable
Scope Five pillars (Carrier, Store, Apps, Cloud, Cable) Targeted: data centers, PoP interconnection, equipment supply chain
Target Entities Broad: China Mobile, China Telecom, China Unicom, Huawei, ZTE, Tencent, Baidu, Alibaba Narrower but deeper: same carriers plus affiliates and third-party users of Huawei/ZTE equipment
Mechanism

"Trusted" list approach; recommended exclusion, voluntary "pledges" from "Clean Countries" and carriers.

Mandatory prohibition; formal rulemaking with enforcement provisions
Carrier Status Policy guidance for U.S. carriers to "avoid" Chinese carriers Direct FCC order prohibiting interconnection with Chinese carriers
Extraterritorial Reach Encouraged allies to adopt similar restrictions Cascading effect: prohibits U.S. carriers from interconnecting with any carrier using Huawei/ZTE equipment globally
Legal Finality Policy statement; subject to administration change Formal regulation; binding until repealed or overturned

 

Key Analyst Assessment: The April 2026 NPRM transforms the Clean Network's voluntary "trusted partner" framework into a mandatory exclusion regime with enforcement teeth. While the Clean Network was a policy articulation, the 2026 NPRM is a formal rulemaking that, if adopted, will carry the force of law. 

While the 2020 Clean Network policy was a "geopolitical vision," the 2026 NPRM is the technical execution.

By banning interconnection and data center operations, the FCC is effectively creating a "Western Firebolt" to mirror China's "Great Firewall."

 

5. Implications for Chinese Carriers

By 2026, Chinese carriers already maintain only a "small presence" in the U.S., primarily through cloud services, wholesale internet traffic routing, Point of Presence (PoP) facilities at internet exchange points, and limited data center operations supporting cross-border enterprise customers.

Consequence Severity Likelihood
Loss of data center operations High High (if rule adopted)
PoP interconnection prohibition High High (if rule adopted)
Cascading international restrictions Medium Medium (depends on allied coordination)
Complete U.S. market exit High High (cumulative effect of multiple bans)

 

6. U.S. Market Dependency Paradox

Analyst Note: A notable irony highlighted by multiple sources: the U.S. data center construction boom is heavily dependent on Chinese supply chains for critical components including transformers, switchgear and batteries. Bloomberg noted that as the global AI race accelerates, U.S. data center expansion faces severe shortages of these components — where Chinese equipment remains "indispensable core supply." As one U.S. academic warned: "If we blindly try to reduce our dependence on China to zero, it could impose excessively high costs on American businesses."
Component U.S. Domestic Production Chinese Supply Dependency
Transformers Severely insufficient High
Switchgear Inadequate High
Batteries Limited High

 

7. China's Response

Chinese Embassy in Washington: China "consistently opposes the overstretching of the concept of national security and the abuse of state power to suppress Chinese enterprises."

Chinese Foreign Ministry Spokesperson Mao Ning (April 2026): "China firmly opposes the US overstretching the concept of national security. This type of action has severely impeded the normal economic and trade exchanges between Chinese and US companies and does not serve anyone's interests, including those of American companies and consumers."

 

8. Analyst Assessment: Strategic Significance

Regulatory Evolution

From equipment bans → carrier operating revocations → data center/PoP prohibition. The "Covered List" is now a comprehensive exclusion mechanism.

Comparison to Clean Network

Clean Network was declaratory policy; 2026 NPRM is operational enforcement. The former said "we prefer trusted partners"; the latter says "interconnection with Chinese carriers is prohibited."

Market Impact

Limited direct revenue impact given already-reduced U.S. presence. Significant symbolic and precedent value for global regulatory coordination.

Geopolitical Signaling

April 30, 2026 vote — coinciding with a companion proposal to ban Chinese labs from device testing — signals comprehensive decoupling in the telecommunications sector.

Cascading Risk

Barring interconnection with any carrier using Huawei/ZTE equipment creates compliance pressure on third-country carriers, accelerating global supply chain bifurcation.

 

9. Conclusion

The FCC's 2026 NPRM represents a significant escalation in the U.S. regulatory posture toward Chinese telecommunications companies. Moving beyond the Clean Network's voluntary framework into mandatory rulemaking, the proposal would effectively sever the remaining commercial ties between Chinese state-owned carriers and the U.S. telecommunications ecosystem.

Traffic between the U.S. and China will no longer be exchanged on U.S. soil; instead, it will be forced through third-party "neutral" hubs like Singapore, Japan, or Europe, significantly increasing latency and cost for U.S.-China digital trade but achieving the U.S. goal of a "Zero-Trust" architecture.

For China Mobile, China Telecom and China Unicom, the practical business impact may be limited given their already diminished U.S. footprint. However, the precedent value is substantial: the "Covered List" mechanism has evolved from equipment procurement restrictions to comprehensive operational prohibitions.

The April 30, 2026 FCC meeting will determine whether this proposal advances to final rulemaking. The telecom industry should monitor the scope of "affiliate" definitions in final rules, implementation timelines for data center divestiture, and international coordination with allied regulators on similar measures.